Fantasmas Incorporated had the following information: ​…

Fantasmas Incorporated had the following information: ​ Activity Driver Unit Variable Cost Level of Activity Driver Units sold $         20    — Setups  1,200    60 Engineering hours     52 1,500       Other data:         Total fixed costs (traditional) $600,000       Total fixed costs (ABC) $360,000       Unit selling price      $         60   ​ What is the break-even point in units using ABC?

Attraction Corporation produces specially machined parts. Th…

Attraction Corporation produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers: Engineering $1,000,000 Setups 900,000 Machining 2,000,000 Inspection 800,000 Providing space 250,000 Providing utilities 180,000 ​ Activity drivers for each activity have been identified and their practical capacities listed: Machine hours 25,000 Setups 200 Engineering hours 5,000 Inspection hours 2,500 ​ The costs of facility-level activities are assigned using machine hours. ​ What is (are) the facility-level activity(ies)?

Edelstein Company had the following data for 2018: Uni…

Edelstein Company had the following data for 2018: Units in process at the beginning of the month 4,000 Units in process at the end of the month 10,000 Units started during the month 40,000 ​ Materials are added at the beginning of the process. Beginning work in process was 40 percent complete as to conversion. Ending work in process was 70 percent complete as to conversion. How many equivalent units for materials would there be using the FIFO method?

Bienestar, Inc., has done a cost analysis for its production…

Bienestar, Inc., has done a cost analysis for its production of vests. The following activities and cost drivers have been developed:   Activity Cost Formula Maintenance $11,000 + $2 per machine hour Machining $55,000 + $3 per machine hour Inspection $70,000 + $500 per batch Setups $2,000 per batch Purchasing $80,000 + $150 per purchase order ​ Following are the actual costs of producing 75,000 vests: 5,000 machine hours; 10 batches; 20 purchase orders   Maintenance $20,000 Machining 73,000 Inspection 73,000 Setups 18,000 Purchasing 82,000 ​ What is the budget variance for setups in an activity-based performance report?

Cumadin Corporation, which manufactures products W, X, Y, an…

Cumadin Corporation, which manufactures products W, X, Y, and Z through a joint process costing $18,000, has the following data for 2018:       Sales Value Product Units Produced at Split-Off    W 10,000 $5,000     X   6,000  2,500    Y 16,000  3,000    Z   8,000 4,500 ​ What is the amount of joint costs assigned to Product X using the sales-value-at-split-off method?

Copies Plus Print operates a copy business at two different…

Copies Plus Print operates a copy business at two different locations. Copies Plus Print has one support department that is responsible for cleaning, service, and maintenance of its copying equipment. The costs of the support department are allocated to each copy center on the basis of total copies made. During the first month, the costs of the support department were expected to be $200,000. Of this amount, $60,000 is considered a fixed cost. During the month, the support department incurred actual variable costs of $128,000 and actual fixed costs of $72,000. Normal and actual activity (copies made) are as follows:   ​ Copy Center 1 Copy Center 2 Normal activity (copies) 600,000 400,000 Actual activity (copies) 500,000 440,000 ​ Support department costs NOT allocated to the two copy centers are:

Diane’s Pottery Manufacturing Company has two support depart…

Diane’s Pottery Manufacturing Company has two support departments, Maintenance Department and Personnel Department, and two producing departments, X and Y. The Maintenance Department costs of $30,000 are allocated on the basis of standard service hours used. The Personnel Department costs of $4,500 are allocated on the basis of number of employees. The direct costs of Departments X and Y are $9,000 and $15,000, respectively. Data on standard service hours and number of employees are as follows:     Maint. Person. Dept. Dept.   Dept. Dept. X Y Standard service hours used 100  75 600 300 Number of employees  50 100 150 150 Direct labor hours 125 125 500 250 ​ What are the total overhead costs associated with Department X after allocating the Maintenance and Personnel Departments using the direct method?