78. Assume for a warehouse construction project the followin…
78. Assume for a warehouse construction project the following percentages of hours spent: holidays 5%, sick leave and vacation 5%, temporary work stoppage due to weather as 10%, and site cleanup as 10%. What was the productive labor yield?