PROJECT CRASHING PROBLEM (all time in Days, all Cost in $):…
PROJECT CRASHING PROBLEM (all time in Days, all Cost in $): What is the total crashing cost to crash the project by 4 days? Activity Immediate Predecessor Normal Time Crash Time Normal Cost Crash Cost A – 5 4 1000 1400 B – 3 3 800 – C A,B 3 1 600 900 D B 4 2 1600 2000 E C,D 5 3 800 1200 F E 2 1 1300 1400