Use the time-phased budget data to complete the status repor…
Use the time-phased budget data to complete the status report for the end of time period 4. Using the time-phased budget data, answer the following: The priorities for this project are as follows: Budget-Accept, Schedule-Enhance, and Performance-Constrain. Based on these priorities, what actions should you take as a project manager based on the project’s performance at the end of time period 4?