At a typical drive-thru customers start by consulting a billboard and placing an order with an employee (via intercom). The customers do not wait for the order to be produced, but proceed directly down the line to pay at the cash register. While customers pay the kitchen staff prepares the order. Finally, (after the payment is completed) the meal is collected at the last window. Placing an order takes on average 60 seconds. Preparing the meal requires 120 seconds. Paying at the cash register requires 50 seconds. Collecting the prepared meal requires 10 seconds. A sample of 10 customers was taken at random, and the average actual flow time was found to be 237.5 seconds. Assume a theoretical flow time of 190 seconds. What is the process flow time efficiency?