A simple project listing of five activities, their predecess…
A simple project listing of five activities, their predecessors, and their respective time estimates are presented below: Activity Immediate Predecessor Time in Days A None 2 B A 2 C A 1 D B and C 3 E D 2 Using CPM, what is the Latest Finish Time for the last activity in this project (i.e., the total time to complete the project)?