6. A project requires the completion of eight activities. The immediate predecessors (predecessors), normal activity time in weeks (normal time), maximum crashing time in weeks (max crash time), and per week crashing cost (crash cost) are shown in the table below. Activity 1 2 3 4 5 6 7 8 predecessors none none none 1,2 1,2,3 3 5,6 4,7 normal time 6 8 7 9 7 7 4 6 max crash time 3 2 3 4 1 2 2 3 crash cost $650 $550 $700 $465 $500 $385 $720 $810 Using the “normal time” values, find and report the early start times, early finish times, late start times, late finish times, and slack for each activity. Identify the critical path and project completion time.