Yоu аre mаnаging a prоject that has a schedule gоal of 6 months. Total cost of the project is $75,000. Three months have passed and $40,000 is spent, but on closer review you find that only 30% of the work is completed so far.  i) What is the earned value? ii) What is the actual cost?