The following is a product structure tree for a toy called zigzag robot (Z-robot). The manufacturer receives an order of 50 units of Z-robot that should be ready in week 10. The lead times for the components are Z (2 weeks), A (1 week), B (1 week), C (1 week), D (1 week), and E (3 weeks). None of these items has inventory on hand. What is the gross requirements for item E?