Mars Corporation uses the percentage-of-completion method. A…
Mars Corporation uses the percentage-of-completion method. At the end of the first year of a $9,000,000 contract, the following information is available: Costs to date: $2,000,000 Estimated costs to complete 6,000,000 Progress billings during the year 1,800,000 Cash collected during the year 1,500,000 At the end of first year, Mars’ balance sheet should report Construction in Progress account of: