A construction project includes a $1.2M cost baseline. The p…
A construction project includes a $1.2M cost baseline. The project manager identifies potential design rework risks and allocates $60,000 within the budget to cover them. Later, an unexpected regulatory change requires redesign of a section of the building, adding $100,000 in new costs not previously identified. Which of the following statements correctly applies project cost reserve concepts?