[launch] The displayed PERT chart shows the necessary tasks…
The displayed PERT chart shows the necessary tasks to get from prototyping the product (node A) to product launch (node H), their dependencies, and the time (months) it takes to move from one task to the next. If the company wants to lower the launch time, which single change listed below will reduce the overall project duration?