A project has the activity duration and cost information ind…
A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for completing this project as quickly as possible?ActivityPredecessorNormal TimeNormal CostCrash TimeCrash CostA–8$12,0005$22,000BA12$18,0009$32,000CA15$22,0009$62,000DB3$9,0002$18,000EC9$15,0005$35,000FE7$5,0005$8,000GD8$13,0006$23,000HA12$20,0008$32,000JH6$45,0004$56,000