A project is being considered by Bulldog Engineering Incorpo…
A project is being considered by Bulldog Engineering Incorporated (BEI). Using estimates from the engineering and finance teams, the project has a project PW of -$6,000 and a projected FW of -$18,500. EBI uses a MARR of 10% for all projects. Should EBI pursue this project? Why or why not?