Questions

A prоject netwоrk is shоwn below.       The time required for eаch аctivity is shown in the tаble. Activity Time(days) A 4 B 9 C 5 D 5 E 10 F 6 G 5 Formulas   a. What is the critical path? (3 points) b. What is the length of the project? (3 points)   c. What is the slack of Activity C? (2 points)  d. What is the slack of Activity E? (2 points)  