A project network is shown below. The time required f…
A project network is shown below. The time required for each activity is shown in the table. Activity Time(days) A 4 B 9 C 5 D 5 E 10 F 6 G 5 Formulas a. What is the critical path? (3 points) b. What is the length of the project? (3 points) c. What is the slack of Activity C? (2 points) d. What is the slack of Activity E? (2 points)