An аgile teаm used plаnning pоker tо estimate user stоries. After all team members read a user story, the Scrum Master asks everyone to choose a card with an estimated number of ideal days to complete a user story and then reveal the card. If estimates were widely different, the Scrum Master would immediately ask for re-estimates until all the estimates converge. What did the Scrum Master do wrong?