Angler Industries produces a product which goes through two…
Angler Industries produces a product which goes through two operations, Assembly and Finishing, before it is ready to be shipped. Next year’s expected costs and activities are shown below. Assembly Finishing Direct labor hours 260,000 DLH 156,000 DLH Machine hours 460,000 MH 128,800 MH Overhead costs $ 460,000 $ 717,600 Assume that Angler Industries allocates overhead using a plantwide overhead rate based on machine hours. How much total overhead will be assigned to a product that requires 2 direct labor hour and 4.10 machine hours in the Assembly Department, and 4.50 direct labor hours and 0.5 machine hours in the Finishing Department?