A health system wants to launch a patient portal. The team d…

A health system wants to launch a patient portal. The team decides to first release appointment scheduling, then later add lab results, and finally billing and messaging. Each feature will be fully finished and usable before moving to the next.Which life cycle does this best describe?

A hospital is implementing a new electronic billing system….

A hospital is implementing a new electronic billing system. The project manager creates a detailed plan at the start, with fixed requirements, timeline, and budget. The team will follow this plan step by step without making major changes.Which life cycle does this best describe?