Skill D2. Consider a workstation that finishes small metal p…
Skill D2. Consider a workstation that finishes small metal parts in a barrel burnishing machine that processes multiple parts at the same time by tumbling. The mean processing time equals 5 minutes (for a batch), and the processing time standard deviation is 2 minutes. The machine can hold up to 100 parts. What is the capacity (parts per hour) of this machine if the batch size is 50 parts?