Stadium Construction Project Problem: What is the latest finish for Activity D? ACTIVITY IMMEDIATE PREDECESSOR DURATION (days) A – 1 B A 4 C A 3 D A 7 E B 6 F C,D 2 G E,F 7 H D 9 I G,H 4