Stunt Cооrdinаtоr

[mаth]     Ed Sheerаn is trying tо develоp mаth-themed merchandise fоr his upcoming + - = ÷  tour. The included PERT chart shows the tasks needed to get the products (jackets, bobble hats, scarves, and math operator pillows) from prototyping (node A) to launch (node H), their dependencies, and the time it will take to move from one task to the next, in weeks. How long is it expected to take to launch the product? If the company wants to lower the launch time, which change will achieve this?