Suppose that you are the project manager of a project with t…
Suppose that you are the project manager of a project with the following project baseline information… estimated project duration of 4 months and an expected project cost of $400,000. How would you determine if the project is meeting the cost and schedule objectives at the end of the first month?What tools/concepts would you employ to assess the project status at the end of the first month?Include a brief description of the info that each tool provides.