Three recent college graduates have formed a partnership and…
Three recent college graduates have formed a partnership and have opened an advertising firm. Their first project consists of activities listed in the following table. What is the probability that the project can be completed in 24 days or less? Time in Days Activity Immediate Predecessor Optimistic Most Likely Pessimistic A – 5 6 7 B – 8 8 11 C A 6 8 10 D – 9 12 15 E C 5 6 9 F D 5 6 7 G F 2 3 7 H B 4 4 5 I H 5 7 8 END E,G,I (Study Guide Question)