Use the excel file provided in question 1 and the info in th…
Use the excel file provided in question 1 and the info in the ‘PERT’ tab to answer the following question. Management wants the project finished within 65 time periods. What is the probability that the project will be finished within 65 time periods? (round your answer to the nearest percentage. Example…47.625 = 48. Don’t include a % sign in your answer)