Vest Co. uses a job-order cost system. The following debits…
Vest Co. uses a job-order cost system. The following debits (credits) appeared in Vest’s work-in-process account for the month of April: April Description Amount 1 Balance $ 4,00030 Direct materials 24,00030 Direct labor 16,00030 Factory overhead 12,80030 To finished goods (48,000) Vest applies overhead to production at a predetermined rate of 80% of direct labor cost. Job No. 5, the only job still in process on April 30, has been charged with direct labor of $2,000. What was the amount of direct materials charged to Job No. 5?