You have determined that the actual number of workstations t…
You have determined that the actual number of workstations that will be used on an assembly line is 6, using the assembly-line balancing procedure. The cycle time of the line is 12 minutes, and the sum of all tasks required on the line is 72 minutes. Which of the following is the correct value for the resulting line’s efficiency?