The following questions relate to the GreenBridge Routing Op…
The following questions relate to the GreenBridge Routing Optimization Project. The project’s critical path is A → B → C → E. Assume the durations shown below are the optimistic, most likely, and pessimistic time estimates in days. Activity Optimistic Most Likely Pessimistic A 1 2 5 B 2 4 7 C 3 6 11 D 2 5 14 E 7 10 16 What is the variance of Activity E?