The following question relates to system integration testing…
The following question relates to system integration testing for the GreenBridge Routing Optimization Project. Based on previous PERT analysis, this effort has an expected completion time of 30 days and a standard deviation of 5 days. Assume completion times are normally distributed. What is the approximate probability that the integration testing effort will be completed within 40 days?