For this exercise, use the information below. The critical p…
For this exercise, use the information below. The critical path (CP) is A, C, & D, and the time/duration is in weeks: PERT Activities.png 1. What is the probability of completing the project in 19 weeks (TS = 19)? 2. What is the probability of completing the project in 22 weeks (TS = 22)? 3. What is the probability of completing the project in 28 weeks (TS = 28)? Note: for full credit, you must show your calculations! z = (TS – TE)/Square Root of Sum of Variances Use the z-score table below (as a hint, if the z-score you calculated is not in the table below, the z-score you calculated is incorrect!): Z-Score Probability -3.0 0.001 -2.0 0.023 -1.0 0.159 0.0 0.500 1.0 0.841 2.0 0.977 3.0 0.998