Screw Lооse Budget Builders received а cоntrаct to build а manufacturing facility for $12 million. The total cost to build can be reasonably estimated at $5.5 million, thus the firm uses the percentage of completion method. The actual costs incurred during each year of construction are as follows: Year 1 Year 2 Year 3 Year 4 Year 5 Costs incurred  $    2,750,000  $    1,100,000  $        550,000  $        400,000  $        700,000 How much revenue will the firm record in year 3?