Two critical path activities are candidates for crashing on…
Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project’s duration, activity ________ should be crashed first, adding ________ to project cost.ActivityNormal TimeNormal CostCrash TimeCrash CostOne8 days$6,0006 days$6,800Two10 days$4,0009 days$5,000