Using the time-phased budget and time period information below, find EV, CV, and SV and evaluate the project’s performance at the end of time period seven (7): EVM Time Phased Budget Exam.png EVM Status Report Exam Question.png Earned Value = CV = SV = Project status at the end of time period seven (7), with regard to budget and schedule. If the project is over budget at this point and/or behind schedule, identify the possible cause and very briefly explain: